MCU lead times are back at 40 to 52 weeks, and the demand looks real
Microcontroller lead times have moved back into shortage territory. Sourceability's third-quarter report, published October 14, put several STMicroelectronics families at 52 weeks and select MCU products at 40 to 52 weeks. Fusion Worldwide's October Greensheet reported Texas Instruments quotes stretching from 12 to 16 weeks toward six months, some beyond 52 weeks, with purchase order decommits.
The question every buyer asks next is whether this is real demand or a rerun of 2021 panic ordering. The evidence this quarter leans toward real, with some padding on top.
The case that it is real
- Avnet (November 4) reported book-to-bill above parity in every region, with demand broad across data center, aerospace and defense, and networking, and a growing backlog as lead times extend.
- Arrow (November 5) reported components book-to-bill well above parity and backlog into mid-2027, with lead times extending but still below the last shortage's peaks.
- Microchip (November 5) reported revenue up 42% year over year, book-to-bill well above one, and a December guide capped by supply rather than demand, with lead times of 6 to 32 weeks.
When distributors and a major MCU maker all describe broad end-market demand and supply-limited shipments, that is a constraint, not just early ordering.
Where the padding is
- Edgewater Research reported in May that Tier 1 suppliers were raising inventory targets from about 4 weeks to as much as 12, and that some suppliers estimated up to 15% of orders were double bookings.
- Price is doing part of the work: Arrow said its third-quarter growth was mostly price, led by memory, and Fusion reported STMicroelectronics price increases of 15 to 30% on automotive grades earlier this year.
- Sentiment is cooling at the edges. ECIA's November Industry Pulse showed the sales outlook down 19.2 points to 112.4.
Our read: underlying demand is real in aerospace, defense, data center and industrial, while automotive and broad-line buyers are adding buffer on top. Padded orders can disappear quickly when lead times turn, which is what made 2023 painful.
What to do this quarter
- Place firm orders for parts with no qualified alternative at current quoted lead times, and do not let them slip into the 52-week bucket.
- Ask for decommit history by part number. A supplier decommitting existing POs is a stronger signal than a quoted lead time.
- Qualify a second source or a pin-compatible family for your top five MCUs by spend and by line-down impact.
- Size buffers to the product, not to a blanket number of weeks: the cost of 12 weeks of stock on every part is real if demand turns.
- Track book-to-bill and cancellations, not just lead times. A falling book-to-bill with high lead times is the early sign of a reversal.
The takeaway
This looks like a genuine constraint with a layer of insurance ordering on top. Protect the parts that would stop a line, avoid padding everything, and watch the demand signals as closely as the lead times.